Part of the Understand how to apply (and tailor) relevant aspects of PRINCE2 processes in context domain, which accounts for 30% of the PRINCE2-PRACTITIONER-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 150-minute exam (~60–100 total, ~18–30 in this domain), expect 3–4 from this objective — we provide 30 practice questions to prepare you well beyond it. (estimate)
Questions 26–30
- 26
A project manager is closing a project that delivered a new logistics system. The project board is satisfied with the product, but the senior user has raised concerns about the handover documentation. What should the project manager do?
Select an answer first - 27
A project manager is closing a project that delivered a new e-commerce platform. The project's risk register shows a residual risk that could affect the platform's performance after handover. What should the project manager do?
Select an answer first - 28
In a project with a very short duration, what is a common tailoring of the Closing a Project process?
Select an answer first - 29
A project manager is closing a project that delivered a new customer portal. The project's issue register shows several issues that were closed as 'won't fix'. What should the project manager do with these issues?
Select an answer first - 30
A small, low-risk project with a single team and a short duration is nearing completion. The project manager wants to tailor the Closing a Project process to be efficient. What is the most appropriate tailoring approach?
Select an answer first