Part of the Understand how to apply (and tailor) relevant aspects of PRINCE2 processes in context domain, which accounts for 30% of the PRINCE2-PRACTITIONER-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 150-minute exam (~60–100 total, ~18–30 in this domain), expect 3–4 from this objective — we provide 30 practice questions to prepare you well beyond it. (estimate)
Questions 6–10
- 6
How is the 'Progress' practice applied in the Closing a Project process?
Select an answer first - 7
In the Closing a Project process, who is responsible for preparing the End Project Report?
Select an answer first - 8
A project manager is closing a project that delivered a new inventory system. The project's business case shows that the expected benefits will only be realized six months after closure. What should the project manager do to ensure the benefits are tracked?
Select an answer first - 9
In a project with a very small project board, the senior user and senior supplier roles are held by the same person. During Closing a Project, what is the most effective way to handle the project board's approval?
Select an answer first - 10
A project manager is closing a project that delivered a new internal tool. The project was run using a hybrid approach, with some agile elements. The project board wants to close the project with a simplified end project report. What is the most appropriate way to tailor the Closing a Project process?
Select an answer first