PRINCE2 Practitioner (Version 7)
4.7 Closing a Project PRINCE2-PRACTITIONER-VERSION-7 Practice Questions (Page 5)
Part of the Understand how to apply (and tailor) relevant aspects of PRINCE2 processes in context domain, which accounts for 30% of the PRINCE2-PRACTITIONER-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 150-minute exam (~60–100 total, ~18–30 in this domain), expect 3–4 from this objective — we provide 30 practice questions to prepare you well beyond it. (estimate)
Questions 21–25
- 21
In a project where the project board is not available for a formal closure meeting, what is an appropriate tailoring of the roles in Closing a Project?
Select an answer first - 22
Which of the following is an objective of the Closing a Project process?
Select an answer first - 23
During the Closing a Project process, the project manager is reviewing the project's plan to ensure all products have been delivered. What should the project manager do if a product is missing?
Select an answer first - 24
A project manager is closing a project that delivered a new compliance system. The project has a very tight deadline, and the project board wants to close the project as quickly as possible. However, the organization's quality department requires a full quality audit before closure. What should the project manager do?
Select an answer first - 25
Which of the following is an output of the Closing a Project process?
Select an answer first
Review the revealed explanations, or continue through the curriculum.