Project Management Professional (PMP)
Domain 2Objective 10
Task 10 Manage Project Closure PMP Practice Questions (Page 7)
Part of the Process domain, which accounts for 41% of the PMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~37–64 in this domain), expect 4–6 from this objective — we provide 34 practice questions to prepare you well beyond it. (estimate)
34questions here
7free pages
7concepts
41%of the exam
Questions 31–34
- 31
Which of the following is an example of a measurable project closure criterion?
Select an answer first - 32
A project manager is closing a software implementation project. The sponsor has verbally confirmed satisfaction with the final product, but the project charter requires written sign-off from the sponsor and the head of operations. The team has already started releasing resources. What should the project manager do FIRST?
Select an answer first - 33
What is the purpose of financial closure activities in a project?
Select an answer first - 34
A project manager is preparing to hand over a new customer relationship management (CRM) system to the IT operations team. The system has passed user acceptance testing, but the operations team has not yet received the runbooks or completed training on the new monitoring tools. What should the project manager do?
Select an answer first
Finished these 4 questions?
Review the revealed explanations, or continue through the curriculum.
No more pagesBack to PMP
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PMP” is a trademark of its owner, used for identification only.