Examers.io
ExamsOrganizationsHow it worksPricingHelp & FAQ
PMI logo

Project Management Professional (PMP)

Domain 2Objective 8

Task 8 Plan and Manage Schedule PMP Practice Questions (Page 1)

Part of the Process domain, which accounts for 41% of the PMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~37–64 in this domain), expect 4–6 from this objective — we provide 32 practice questions to prepare you well beyond it. (estimate)

32questions here
7free pages
8concepts
41%of the exam

Questions 1–5

  1. 1application · medium

    A project manager is estimating the duration of a task that is similar to tasks completed in previous projects. The historical data shows a range of 10-15 days, with an average of 12 days. The current task has a known complexity increase that typically adds 20% to duration. What is the most appropriate estimate?

    Select an answer first
  2. 2foundation · easy

    What is the primary benefit of using historical data from past projects when estimating task durations?

    Select an answer first
  3. 3foundation · easy

    Which tool is commonly used to create a project schedule with dependencies and critical path analysis?

    Select an answer first
  4. 4foundation · easy

    When should the schedule baseline be updated?

    Select an answer first
  5. 5application · medium

    A project manager has established the schedule baseline. During execution, a change request is approved that adds a new feature, extending the project by two weeks. What should the project manager do?

    Select an answer first
Finished these 5 questions?

Review the revealed explanations, or continue through the curriculum.

Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PMP” is a trademark of its owner, used for identification only.