Examers.io
ExamsOrganizationsHow it worksPricingHelp & FAQ
PMI logo

Project Management Professional (PMP)

Domain 2Objective 8

Task 8 Plan and Manage Schedule PMP Practice Questions (Page 3)

Part of the Process domain, which accounts for 41% of the PMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~37–64 in this domain), expect 4–6 from this objective — we provide 32 practice questions to prepare you well beyond it. (estimate)

32questions here
7free pages
8concepts
41%of the exam

Questions 11–15

  1. 11foundation · easy

    Which estimation technique uses milestones as reference points to estimate task durations?

    Select an answer first
  2. 12foundation · easy

    What is the primary purpose of executing the schedule management plan?

    Select an answer first
  3. 13application · medium

    A project manager is monitoring the schedule. The project is currently 10% behind schedule. The project manager has identified that the delay is due to a vendor's late delivery. What is the most appropriate corrective action?

    Select an answer first
  4. 14expert · hard

    A project has a schedule variance of -10 days. The critical path has 5 days of float. The project manager has the option to fast-track two activities, which would save 3 days but increase risk, or crash an activity, which would save 5 days but increase cost. The project sponsor is risk-averse but cost-conscious. What should the project manager do?

    Select an answer first
  5. 15foundation · easy

    What is a schedule baseline?

    Select an answer first
Finished these 5 questions?

Review the revealed explanations, or continue through the curriculum.

Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PMP” is a trademark of its owner, used for identification only.