Questions 11–15
- 11
Which estimation technique uses milestones as reference points to estimate task durations?
Select an answer first - 12
What is the primary purpose of executing the schedule management plan?
Select an answer first - 13
A project manager is monitoring the schedule. The project is currently 10% behind schedule. The project manager has identified that the delay is due to a vendor's late delivery. What is the most appropriate corrective action?
Select an answer first - 14
A project has a schedule variance of -10 days. The critical path has 5 days of float. The project manager has the option to fast-track two activities, which would save 3 days but increase risk, or crash an activity, which would save 5 days but increase cost. The project sponsor is risk-averse but cost-conscious. What should the project manager do?
Select an answer first - 15
What is a schedule baseline?
Select an answer first