Task 10 Manage Project Closure PMP Practice Questions (Page 1)
Part of the Process domain, which accounts for 41% of the PMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~37–64 in this domain), expect 4–6 from this objective — we provide 34 practice questions to prepare you well beyond it. (estimate)
34questions here
7free pages
7concepts
41%of the exam
Questions 1–5
- 1
What does transition readiness validation assess before handing over project outputs to the operations team?
Select an answer first - 2
A project manager is closing a project that developed a new customer service platform. The platform is ready for handover, but the operations team has not yet been trained. The project team includes several key developers who are also needed for the next project, which starts next week. The sponsor wants to close the current project on time. What should the project manager do?
Select an answer first - 3
A project manager is closing a project that had a contract with a vendor. The vendor has completed all work, but there is a dispute over the final invoice amount. The vendor claims the project manager approved additional work that was not in the original contract. The project manager does not recall approving the additional work. What should the project manager do?
Select an answer first - 4
A project manager is closing a project that implemented a new payroll system. The system has been tested and is ready for handover, but the operations team is understaffed and cannot complete the required training before the project's planned closure date. The sponsor wants to close the project on time to meet a regulatory deadline. What should the project manager do?
Select an answer first - 5
A project manager is closing a project that has several outstanding invoices from vendors. The finance department has a strict policy that all invoices must be paid within 30 days of receipt. The project manager has received all invoices, but the project budget is running low. What should the project manager do?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.