Task 9 Evaluate Project Status PMP Practice Questions (Page 1)
Part of the Process domain, which accounts for 41% of the PMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~37–64 in this domain), expect 4–6 from this objective — we provide 34 practice questions to prepare you well beyond it. (estimate)
34questions here
7free pages
9concepts
41%of the exam
Questions 1–5
- 1
During a monthly status review, the project manager notices that the reported percent complete for a work package is 80%, but the actual deliverables are only 50% complete. The team lead explains that the percent complete was estimated based on effort spent, not on deliverables. The project manager needs to ensure accurate project status. What should the project manager do first?
Select an answer first - 2
A project manager is defining metrics for a new software development project. Which action best ensures that the metrics align with project objectives and stakeholder needs?
Select an answer first - 3
A project manager is preparing the monthly status report for a project that is behind schedule but under budget. The sponsor is primarily concerned about the schedule, while the project team is concerned about the budget. The project manager needs to communicate the status in a way that addresses both concerns. What should the project manager do?
Select an answer first - 4
What is the purpose of continuously evaluating artifact management effectiveness?
Select an answer first - 5
A project manager is assessing the current progress of a project. Which activity is most directly part of this assessment?
Select an answer first