Task 9 Evaluate Project Status PMP Practice Questions (Page 7)

Part of the Process domain, which accounts for 41% of the PMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~37–64 in this domain), expect 4–6 from this objective — we provide 34 practice questions to prepare you well beyond it. (estimate)

34questions here
7free pages
9concepts
41%of the exam

Questions 31–34

  1. 31application · medium

    A project manager is tracking a project's progress using a key performance indicator (KPI) of 'number of features delivered per sprint.' After three sprints, the team consistently delivers 5 features per sprint, but the project is falling behind schedule because the scope includes more features than originally estimated. The project manager needs to update the project metrics to better reflect progress. What should the project manager do?

    Select an answer first
  2. 32foundation · easy

    What is the main benefit of analyzing project data to identify trends and variances?

    Select an answer first
  3. 33application · medium

    A software development project is in its third month. The project manager needs to select metrics to track progress and report to stakeholders. The sponsor cares about delivering features on time, while the development team wants to monitor code quality. The project manager wants to avoid overwhelming the team with excessive data collection. Which set of metrics best balances stakeholder needs and team workload?

    Select an answer first
  4. 34expert · hard

    A project manager is leading a project to implement a new customer relationship management (CRM) system. The project has multiple stakeholders with different priorities: the sales team wants to track leads, the marketing team wants to track campaigns, and the IT team wants to ensure system performance. The project manager needs to select metrics that will satisfy all stakeholders without overwhelming the team. What should the project manager do?

    Select an answer first
Finished these 4 questions?

Review the revealed explanations, or continue through the curriculum.

No more pagesBack to PMP

Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PMP” is a trademark of its owner, used for identification only.