Project Management Professional (PMP)
Domain 2Objective 8
Task 8 Plan and Manage Schedule PMP Practice Questions (Page 7)
Part of the Process domain, which accounts for 41% of the PMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~37–64 in this domain), expect 4–6 from this objective — we provide 32 practice questions to prepare you well beyond it. (estimate)
32questions here
7free pages
8concepts
41%of the exam
Questions 31–32
- 31
A project manager is estimating the duration for a task that involves migrating a legacy system. The organization has completed similar migrations in the past, with durations ranging from 4 to 8 weeks. The current project has a slightly more complex data structure. What is the most appropriate way to use historical data?
Select an answer first - 32
A project manager is coordinating with another project that shares a critical resource. The other project's schedule has a high-priority task that requires the same resource during the same period. What should the project manager do?
Select an answer first
Finished these 2 questions?
Review the revealed explanations, or continue through the curriculum.
No more pagesBack to PMP