Task 8 Plan and Manage Schedule PMP Practice Questions (Page 2)

Part of the Process domain, which accounts for 41% of the PMP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~37–64 in this domain), expect 4–6 from this objective — we provide 32 practice questions to prepare you well beyond it. (estimate)

32questions here
7free pages
8concepts
41%of the exam

Questions 6–10

  1. 6foundation · easy

    What is the primary purpose of inter-project coordination in schedule management?

    Select an answer first
  2. 7application · medium

    A construction project's schedule depends on the completion of a foundation pour by another project in the same program. The other project's schedule is delayed by two weeks. What should the project manager do first?

    Select an answer first
  3. 8application · medium

    A project is using earned value management. The project manager calculates SPI = 0.9 and CPI = 1.1. What is the most appropriate action?

    Select an answer first
  4. 9application · medium

    A software development team is using a hybrid approach: a predictive plan for the infrastructure phase and an agile approach for the feature development phase. The team uses story points for features and duration estimates for infrastructure tasks. During sprint planning, they need to create a schedule that integrates both phases. What should the project manager do?

    Select an answer first
  5. 10foundation · easy

    What is schedule variance (SV)?

    Select an answer first