Task 3 Establish Scheduling Policies and Procedures Regarding Methodology, Selection of a Scheduling Tool, Scheduling Parameters, Performance Thresholds, Activity Granularity, Presentation Format, Earned Value Management (EVM) Implementation, Analysis Techniques, and Approval Requirements by Using Resources Such as Organizational Process Assets and Project Documents in Order to Develop the Schedule Management Plan and Standardize Operational Procedures. PMI-SP Practice Questions (Page 8)
Part of the Schedule Strategy domain, which accounts for 14% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~13–22 in this domain), expect 3–4 from this objective — we provide 38 practice questions to prepare you well beyond it. (estimate)
38questions here
8free pages
13concepts
14%of the exam
Questions 36–38
- 36
What does 'activity granularity' refer to in schedule development?
Select an answer first - 37
A project manager is creating the schedule for a complex engineering project. The team includes specialists who need to track their work in detail, but the sponsor only wants a high-level view. The organization's process assets require that all schedules use a consistent level of detail. What should the project manager do?
Select an answer first - 38
A project manager is implementing EVM for a new project. The organization has a standard EVM methodology, but the project has a short duration (3 months) and a small budget. The project manager must plan the EVM implementation. What should the project manager do?
Select an answer first
Finished these 3 questions?
Review the revealed explanations, or continue through the curriculum.
No more pagesBack to PMI-SP
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PMI-SP” is a trademark of its owner, used for identification only.