PMIScheduling Professional (PMI-SP)
Domain 1Objective 4
Task 4 Develop the Scheduling-Related Components for Project Management Plans (for Example, Integration, Scope, Cost, Quality, Resources, Communication, Risk, and Procurement Management), Through Review of Contract Requirements, in Order to Integrate Scheduling Activities into the Overall Project Management Process. PMI-SP Practice Questions (Page 1)
Part of the Schedule Strategy domain, which accounts for 14% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~13–22 in this domain), expect 3–4 from this objective — we provide 18 practice questions to prepare you well beyond it. (estimate)
18questions here
4free pages
3concepts
14%of the exam
Questions 1–5
- 1
A project manager is developing the quality management plan and must ensure that quality control activities are integrated with the schedule. The contract specifies that quality audits must be completed before the final acceptance milestone. The project manager needs to schedule these audits without delaying the project. Which approach best integrates quality audits into the schedule?
Select an answer first - 2
A project manager is developing the communications management plan and must ensure that schedule reporting meets contractual obligations. The contract requires weekly progress reports that include schedule variance analysis. Which scheduling component should be incorporated into the communications management plan?
Select an answer first - 3
A project manager is updating the resource management plan and needs to ensure that resource allocation aligns with the project schedule. Which scheduling-related component should be integrated into the resource management plan?
Select an answer first - 4
A software development project has a contract that specifies a fixed delivery date and includes a liquidated damages clause for late delivery. The project manager is developing the schedule management plan and must balance the contractual deadline with the need for quality assurance. Which approach best integrates scheduling with the quality management plan to mitigate the risk of late delivery?
Select an answer first - 5
Which activity is an example of integrating scheduling into the overall project management process?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.