Task 2 Develop Schedule Approach, Based on the Unique Characteristics of the Project, Including Enterprise Environmental Factors and Organizational Process Assets, in Order to Define Schedule Requirements. PMI-SP Practice Questions (Page 1)

Part of the Schedule Strategy domain, which accounts for 14% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~13–22 in this domain), expect 3–4 from this objective — we provide 20 practice questions to prepare you well beyond it. (estimate)

20questions here
4free pages
5concepts
14%of the exam

Questions 1–5

  1. 1application · medium

    A project manager is planning a project that has a very large scope and a long duration. The organization has a culture that values detailed planning and control. The PM needs to select a schedule approach. What should the PM choose?

    Select an answer first
  2. 2expert · hard

    A project manager is working on a project where the organization has a standard scheduling template that is designed for predictive projects. However, the project is best suited for an agile approach. The PM needs to decide how to handle this conflict. What should the PM do?

    Select an answer first
  3. 3foundation · easy

    During the development of a project schedule, which of the following is an example of an enterprise environmental factor that could influence the selection of a schedule approach?

    Select an answer first
  4. 4application · medium

    A project manager is developing the schedule for a construction project. The organization has a standard scheduling template and historical data from similar past projects. The PM wants to ensure the schedule approach aligns with organizational practices. What should the PM do first?

    Select an answer first
  5. 5application · medium

    A project manager is selecting a schedule approach for a project that has a moderate level of uncertainty and a well-defined core scope. The organization has experience with both predictive and agile methods. The PM needs to balance flexibility with structure. What should the PM choose?

    Select an answer first
Finished these 5 questions?

Review the revealed explanations, or continue through the curriculum.