Task 3 Establish Scheduling Policies and Procedures Regarding Methodology, Selection of a Scheduling Tool, Scheduling Parameters, Performance Thresholds, Activity Granularity, Presentation Format, Earned Value Management (EVM) Implementation, Analysis Techniques, and Approval Requirements by Using Resources Such as Organizational Process Assets and Project Documents in Order to Develop the Schedule Management Plan and Standardize Operational Procedures. PMI-SP Practice Questions (Page 1)

Part of the Schedule Strategy domain, which accounts for 14% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~13–22 in this domain), expect 3–4 from this objective — we provide 38 practice questions to prepare you well beyond it. (estimate)

38questions here
8free pages
13concepts
14%of the exam

Questions 1–5

  1. 1foundation · easy

    Which factor should influence the level of activity granularity in a schedule?

    Select an answer first
  2. 2foundation · easy

    What are organizational process assets?

    Select an answer first
  3. 3application · hard

    A global software company is launching a new mobile app with a fixed release date, a small cross-functional team of 8, and a product owner who will prioritize features each sprint. The organization's process assets mandate a formal schedule baseline and earned value reporting for all projects. The project manager must select a scheduling methodology. What should the project manager do?

    Select an answer first
  4. 4foundation · easy

    What does 'level of accuracy' refer to in scheduling parameters?

    Select an answer first
  5. 5application · medium

    A project manager is defining the approval requirements for schedule changes in the schedule management plan. The project has a change control board (CCB) that reviews all changes. The project manager wants to ensure that schedule changes are reviewed appropriately without overburdening the CCB. What should the project manager specify?

    Select an answer first