Examers.io
ExamsOrganizationsHow it worksPricingHelp & FAQ
PMI logo

PMIScheduling Professional (PMI-SP)

Domain 1Objective 3

Task 3 Establish Scheduling Policies and Procedures Regarding Methodology, Selection of a Scheduling Tool, Scheduling Parameters, Performance Thresholds, Activity Granularity, Presentation Format, Earned Value Management (EVM) Implementation, Analysis Techniques, and Approval Requirements by Using Resources Such as Organizational Process Assets and Project Documents in Order to Develop the Schedule Management Plan and Standardize Operational Procedures. PMI-SP Practice Questions (Page 3)

Part of the Schedule Strategy domain, which accounts for 14% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~13–22 in this domain), expect 3–4 from this objective — we provide 38 practice questions to prepare you well beyond it. (estimate)

38questions here
8free pages
13concepts
14%of the exam

Questions 11–15

  1. 11foundation · easy

    A project has well-defined requirements and a fixed delivery date. Which scheduling methodology is most appropriate?

    Select an answer first
  2. 12expert · hard

    A project manager is developing the schedule for a research and development project with high uncertainty in task durations and dependencies. The sponsor wants a probabilistic estimate of the project completion date, not just a single date. The project manager must select an analysis technique. What should the project manager do?

    Select an answer first
  3. 13application · medium

    A project manager is developing the schedule management plan for a project with stakeholders who have different reporting needs. The executive sponsor wants a high-level dashboard, the project team wants detailed task lists, and the client wants a milestone chart. The project manager must specify the presentation format. What should the project manager do?

    Select an answer first
  4. 14foundation · easy

    What is the purpose of specifying the presentation format for schedule reports?

    Select an answer first
  5. 15application · medium

    A PMO is updating its scheduling procedures to ensure consistency across all projects. Currently, each project manager uses different reporting formats and approval processes. The PMO wants to standardize these procedures. What should the PMO do?

    Select an answer first
Finished these 5 questions?

Review the revealed explanations, or continue through the curriculum.

Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PMI-SP” is a trademark of its owner, used for identification only.