PMIScheduling Professional (PMI-SP)
Domain 1Objective 3
Task 3 Establish Scheduling Policies and Procedures Regarding Methodology, Selection of a Scheduling Tool, Scheduling Parameters, Performance Thresholds, Activity Granularity, Presentation Format, Earned Value Management (EVM) Implementation, Analysis Techniques, and Approval Requirements by Using Resources Such as Organizational Process Assets and Project Documents in Order to Develop the Schedule Management Plan and Standardize Operational Procedures. PMI-SP Practice Questions (Page 7)
Part of the Schedule Strategy domain, which accounts for 14% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~13–22 in this domain), expect 3–4 from this objective — we provide 38 practice questions to prepare you well beyond it. (estimate)
38questions here
8free pages
13concepts
14%of the exam
Questions 31–35
- 31
Why is it important to define approval requirements for schedule changes?
Select an answer first - 32
Who is typically responsible for approving changes to the project schedule baseline?
Select an answer first - 33
A project manager is defining the scheduling parameters for a project that spans multiple countries and time zones. The team works in different locations, and the project manager must decide on the calendar units and units of measure for the schedule. What should the project manager do?
Select an answer first - 34
A project manager is developing the schedule management plan for a project that has a very detailed work breakdown structure (WBS) with work packages at a low level. The project manager must define the scheduling parameters and activity granularity. What should the project manager do?
Select an answer first - 35
How do project documents help in establishing scheduling policies?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.