PMIScheduling Professional (PMI-SP)
Domain 1Objective 4
Task 4 Develop the Scheduling-Related Components for Project Management Plans (for Example, Integration, Scope, Cost, Quality, Resources, Communication, Risk, and Procurement Management), Through Review of Contract Requirements, in Order to Integrate Scheduling Activities into the Overall Project Management Process. PMI-SP Practice Questions (Page 4)
Part of the Schedule Strategy domain, which accounts for 14% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~13–22 in this domain), expect 3–4 from this objective — we provide 18 practice questions to prepare you well beyond it. (estimate)
18questions here
4free pages
3concepts
14%of the exam
Questions 16–18
- 16
A project manager is developing the cost management plan and needs to ensure that the schedule and cost baselines are aligned. Which scheduling-related component should be included in the cost management plan to support this alignment?
Select an answer first - 17
A project manager is developing the resource management plan and needs to ensure that the schedule accounts for resource availability and constraints. Which scheduling-related component should be integrated into the resource management plan?
Select an answer first - 18
A project manager is developing the risk management plan and must address the risk of schedule delays due to potential vendor non-performance. The contract includes a penalty clause for late delivery. The project manager needs to integrate risk management with the schedule to mitigate this risk. Which approach best integrates schedule risk management?
Select an answer first
Finished these 3 questions?
Review the revealed explanations, or continue through the curriculum.