Task 5 Archive Schedule Files (for Example, Final Schedule Model, Schedule Management Plan, Periodic Status Reports, Schedule Change Log), as per Defined Procedures in Order to Satisfy Contractual Requirements and Prepare for Potential Forensic Schedule Analysis. PMI-SP Practice Questions (Page 5)

Part of the Schedule Closeout domain, which accounts for 6% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~5–9 in this domain), expect 1–2 from this objective — we provide 23 practice questions to prepare you well beyond it. (estimate)

23questions here
5free pages
4concepts
6%of the exam

Questions 21–23

  1. 21application · medium

    A construction firm is closing out a highway project. The contract states that at project completion, the contractor must deliver a complete set of schedule records, including the final schedule model, the schedule management plan, all monthly status reports, and the schedule change log. The project manager has collected these documents, but the final schedule model is in the native scheduling software format and the contract only specifies 'final schedule model' without a format. What should the project manager do to best satisfy the contractual requirement?

    Select an answer first
  2. 22application · medium

    A project scheduler is preparing the archive for a completed software development project. The project used an agile approach, and the schedule was updated in two-week sprints. The scheduler has the final schedule model and the schedule management plan. Which additional files are essential to include in the archive to support a potential forensic schedule analysis?

    Select an answer first
  3. 23expert · hard

    A project manager is archiving schedule files for a completed project. The organization's procedure requires that the archive be stored in a secure repository with access logs, and that all files be versioned and time-stamped. The project manager has archived the final schedule model and the schedule management plan, but the schedule change log is missing some entries due to a data entry error. The project manager is considering whether to correct the log or archive it as-is. What is the best action?

    Select an answer first
Finished these 3 questions?

Review the revealed explanations, or continue through the curriculum.