Task 5 Archive Schedule Files (for Example, Final Schedule Model, Schedule Management Plan, Periodic Status Reports, Schedule Change Log), as per Defined Procedures in Order to Satisfy Contractual Requirements and Prepare for Potential Forensic Schedule Analysis. PMI-SP Practice Questions (Page 4)

Part of the Schedule Closeout domain, which accounts for 6% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~5–9 in this domain), expect 1–2 from this objective — we provide 23 practice questions to prepare you well beyond it. (estimate)

23questions here
5free pages
4concepts
6%of the exam

Questions 16–20

  1. 16foundation · easy

    What is the primary purpose of following defined procedures when archiving schedule files?

    Select an answer first
  2. 17expert · hard

    A project manager is archiving schedule files for a completed project. The organization's procedure requires that all schedule files be archived in a specific document management system with restricted access, and that the archive be retained for five years. The project manager has archived the final schedule model and the schedule management plan, but the schedule change log is still being finalized by the scheduler. The contract requires the archive to be delivered within 10 business days. What should the project manager do to balance the procedure and the contractual deadline?

    Select an answer first
  3. 18foundation · easy

    Which of the following is a type of schedule file that should be archived during schedule closeout?

    Select an answer first
  4. 19expert · hard

    A project manager is closing a project that experienced significant delays and disputes. The contract requires the archive to include the final schedule model, all periodic status reports, and the schedule change log. The project manager has all these files, but some status reports are missing data due to a software upgrade. The client is considering a claim, and the project manager wants to prepare for forensic schedule analysis. What is the best action?

    Select an answer first
  5. 20application · medium

    A contractor is closing a project where the contract states that the schedule archive must be delivered in both electronic and printed formats. The project manager has prepared the electronic archive but is unsure whether the printed copy must include all documents or just the final schedule model. What should the project manager do?

    Select an answer first
Finished these 5 questions?

Review the revealed explanations, or continue through the curriculum.