Part of the Domain 2 Leadership domain, which accounts for 25% of the PMI-ACP exam. PMI does not publish an official question count, but from its 180-minute exam (~70–120 total, ~18–30 in this domain), expect 3–5 from this objective — we provide 23 practice questions to prepare you well beyond it. (estimate)

23questions here
5free pages
3concepts
25%of the exam

Questions 1–5

  1. 1application · medium

    A team member is consistently late to daily stand-ups and has become withdrawn. The agile coach learns that the team member is frustrated because they feel their ideas are ignored by the rest of the team. The coach wants to address this conflict. Which approach best matches the conflict level and supports collaborative resolution?

    Select an answer first
  2. 2application · medium

    A team is experiencing conflicts because some members feel others are not pulling their weight. The agile coach observes that the conflict is actually due to unclear role definitions. What is the BEST way to address the root cause?

    Select an answer first
  3. 3application · medium

    A conflict has arisen between two feature teams in the same program. They are competing for the same shared resource (a database administrator) and are blaming each other for delays. The program manager wants to resolve this. What is the FIRST step?

    Select an answer first
  4. 4expert · hard

    An agile team has been in conflict with the quality assurance (QA) team because the QA team keeps rejecting stories that developers believe are complete. The conflict is recurring and is causing delays. The agile coach suspects the root cause is a different understanding of 'done'. Which approach is MOST effective?

    Select an answer first
  5. 5application · medium

    A team is experiencing frequent conflicts during sprint reviews because stakeholders keep changing requirements. The team is frustrated and feels their work is not valued. The agile coach wants to address the root cause of the conflict. What is the most appropriate first step?

    Select an answer first