Task 5 Promote Shared Vision and Purpose PMI-ACP Practice Questions (Page 1)

Part of the Domain 2 Leadership domain, which accounts for 25% of the PMI-ACP exam. PMI does not publish an official question count, but from its 180-minute exam (~70–120 total, ~18–30 in this domain), expect 3–5 from this objective — we provide 22 practice questions to prepare you well beyond it. (estimate)

22questions here
5free pages
3concepts
25%of the exam

Questions 1–5

  1. 1foundation · easy

    During a sprint review, a stakeholder suggests adding a feature that is not aligned with the product vision. What is the most appropriate action for the product owner?

    Select an answer first
  2. 2application · medium

    During a sprint, a developer identifies a technical solution that would significantly reduce the time to implement a feature. However, the solution would require using a technology that is not part of the product's long-term vision. The developer is excited about the efficiency gain. What should the developer do?

    Select an answer first
  3. 3application · medium

    A new agile team is being formed to develop a product for a rapidly changing market. The team has diverse backgrounds and different ideas about what the product should be. The project sponsor wants the team to have a clear direction before they start working. What is the most effective way to establish a shared vision and purpose for the team?

    Select an answer first
  4. 4expert · hard

    An agile team is developing a product for a highly regulated industry. The product vision emphasizes innovation and speed to market, but the organization's compliance requirements are strict and may slow down development. The team is frustrated with the compliance processes and believes they are hindering the vision. What should the product owner do?

    Select an answer first
  5. 5application · medium

    A product owner on an agile team is preparing for the next sprint planning session. The team has been delivering features, but stakeholders from different departments have expressed confusion about how the features connect to the company's strategic direction. The product owner wants to ensure everyone has a shared understanding of the project's purpose before the team commits to the next sprint's work. What should the product owner do first?

    Select an answer first