Closing PGMP Practice Questions (Page 1)

Part of the Program Life Cycle Management domain, which accounts for 44% of the PGMP exam. PMI does not publish an official question count, but from its 240-minute exam (~95–160 total, ~42–70 in this domain), expect 8–14 from this objective — we provide 32 practice questions to prepare you well beyond it. (estimate)

32questions here
7free pages
8concepts
44%of the exam

Questions 1–5

  1. 1expert · hard

    A program that implemented a new patient scheduling system is closing. The program's benefits include reduced wait times and improved patient satisfaction. The program manager must transition the system's ongoing support to the hospital's IT department. However, the IT department has limited resources and cannot take on the support immediately. The program manager needs to ensure that the benefits are sustained. What should the program manager do?

    Select an answer first
  2. 2foundation · easy

    What is the purpose of updating the Program Management Information System (PMIS) during administrative closure?

    Select an answer first
  3. 3application · medium

    A program manager is closing a program that delivered a new mobile banking app. The program manager has gathered lessons learned from the team and stakeholders. The organization's knowledge repository is the central location for storing lessons learned. What should the program manager do to ensure that the lessons learned are available for future programs?

    Select an answer first
  4. 4foundation · easy

    What does effective benefits transition during program closure ensure?

    Select an answer first
  5. 5expert · hard

    A program manager is closing a program that delivered a new claims processing system. The governance framework requires that the closure plan be approved by the finance director and the program sponsor. The program manager has prepared the closure plan, but the finance director is on leave for two weeks. The program's benefits are already being realized, and the operations team is ready to take over. What should the program manager do?

    Select an answer first