Examers.io
ExamsOrganizationsHow it worksPricingHelp & FAQ
PMI logo

PMIProgram Management Professional (PgMP)

Domain 1Objective 1

Define Program Direction and Alignment PGMP Practice Questions (Page 1)

Part of the Strategic Program Alignment domain, which accounts for 15% of the PGMP exam. PMI does not publish an official question count, but from its 240-minute exam (~95–160 total, ~14–24 in this domain), expect 4–6 from this objective — we provide 28 practice questions to prepare you well beyond it. (estimate)

28questions here
6free pages
7concepts
15%of the exam

Questions 1–5

  1. 1application · medium

    A renewable energy company is evaluating a program to build a wind farm. The business case shows good returns, but the program would have visual and noise impacts on nearby communities. The program manager must assess the program's readiness. What should the program manager do?

    Select an answer first
  2. 2expert · hard

    A pharmaceutical company is planning a program to develop a new drug. The drug has potential to treat a rare disease, but the clinical trials involve a vulnerable population. The business case is strong, but there are ethical concerns about informed consent and data privacy. The program manager must ensure the program is deliverable and aligned with ethical standards. What should the program manager do?

    Select an answer first
  3. 3expert · hard

    An energy company is planning a program to build a new pipeline. The program will create jobs and improve energy security, but it will pass through indigenous lands, raising cultural and environmental concerns. The company's strategic plan emphasizes sustainability and community relations. The program manager must align program objectives with stakeholder expectations. What should the program manager do?

    Select an answer first
  4. 4foundation · easy

    What is the primary purpose of the initial program assessment?

    Select an answer first
  5. 5application · medium

    A construction program is planned in a region with strict environmental regulations. The business case is strong, but the program would require clearing a protected forest area. The program manager must ensure compliance and deliverability. What should the program manager do?

    Select an answer first
Finished these 5 questions?

Review the revealed explanations, or continue through the curriculum.

Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PGMP” is a trademark of its owner, used for identification only.