Examers.io
ExamsOrganizationsHow it worksPricingHelp & FAQ
PMI logo

PMIProgram Management Professional (PgMP)

Domain 3Objective 3

Benefits Sustainment PGMP Practice Questions (Page 1)

Part of the Benefits Management domain, which accounts for 11% of the PGMP exam. PMI does not publish an official question count, but from its 240-minute exam (~95–160 total, ~10–18 in this domain), expect 2–4 from this objective — we provide 30 practice questions to prepare you well beyond it. (estimate)

30questions here
6free pages
6concepts
11%of the exam

Questions 1–5

  1. 1application · medium

    A program has delivered a new online appointment scheduling system for a clinic. The program's intended benefit is to reduce patient wait times. The sustainment plan needs a metric to track this benefit. Which metric would be most appropriate?

    Select an answer first
  2. 2application · medium

    A program that delivered a new customer relationship management (CRM) system is nearing completion. The program manager is developing the transition plan to hand over the system to the IT operations team. The operations team has not been involved in the program and lacks knowledge of the system's architecture and support procedures. Which action should the program manager take to best ensure benefit sustainment?

    Select an answer first
  3. 3foundation · easy

    What is a key element of a transition plan to operations?

    Select an answer first
  4. 4application · medium

    A program has delivered a new employee self-service HR portal. The program manager is developing the sustainment plan. The plan must include a way to track whether the portal is reducing the number of HR inquiries. Which component should the sustainment plan include?

    Select an answer first
  5. 5expert · hard

    A program has delivered a new online learning system for a large university. The sustainment plan assigns the IT department the responsibility of ensuring the system continues to deliver the benefit of improved student engagement. The IT department is focused on system uptime and performance, not on educational outcomes. The program manager is concerned that the IT department may not effectively monitor the engagement benefit. What should the program manager do?

    Select an answer first
Finished these 5 questions?

Review the revealed explanations, or continue through the curriculum.

Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PGMP” is a trademark of its owner, used for identification only.