Benefits Transition PGMP Practice Questions (Page 1)
Part of the Benefits Management domain, which accounts for 11% of the PGMP exam. PMI does not publish an official question count, but from its 240-minute exam (~95–160 total, ~10–18 in this domain), expect 2–4 from this objective — we provide 15 practice questions to prepare you well beyond it. (estimate)
15questions here
3free pages
1concept
11%of the exam
Questions 1–5
- 1
A large-scale public infrastructure program is transitioning from project delivery to operations. The program's benefits realization plan defines three key benefits: (1) reduce traffic congestion by 20%, (2) improve air quality by 15%, and (3) increase public transit ridership by 10%. All targets are to be measured within one year of full deployment. The program has been fully deployed for one year. The program manager receives the following data: traffic congestion is down 22%, air quality is improved by 12%, and transit ridership is up 8%. The program sponsor is pressuring the program manager to close the program, citing the congestion reduction as evidence of success. The program manager is preparing for the final benefits review. What should the program manager do?
Select an answer first - 2
A program is transitioning its final component's outputs to operations. What is the primary purpose of verifying benefit realization criteria during this transition?
Select an answer first - 3
A multinational corporation is transitioning a global ERP program from project delivery to operations. The program's benefits realization plan defines the benefit as 'standardizing business processes across all regions, resulting in a 15% reduction in operational costs within two years of full deployment.' The program has been fully deployed for two years. The program manager receives the following data: operational costs have decreased by 12% globally, but the reduction varies significantly by region. The European region achieved a 20% reduction, while the Asian region achieved only a 5% reduction. The program sponsor asks the program manager to close the program, citing the overall 12% reduction as a positive outcome. What should the program manager do?
Select an answer first - 4
A government program is transitioning from project delivery to operations. The program's benefits realization plan specifies that the new citizen portal must achieve a 90% user satisfaction score within six months of launch. The portal has been live for five months, and the latest survey shows an 88% satisfaction score. The program manager is preparing for the final benefits review. What should the program manager do?
Select an answer first - 5
A financial services program is transitioning from project delivery to operations. The program's benefits realization plan states that the new fraud detection system must reduce false positives by 30% while maintaining a 99.5% detection rate. The system has been live for two months. The program manager receives the following data: false positives are down 32%, but the detection rate is 99.2%. The program manager is preparing for the benefits transition review. What should the program manager do?
Select an answer first