Benefits Transition PGMP Practice Questions (Page 3)
Part of the Benefits Management domain, which accounts for 11% of the PGMP exam. PMI does not publish an official question count, but from its 240-minute exam (~95–160 total, ~10–18 in this domain), expect 2–4 from this objective — we provide 15 practice questions to prepare you well beyond it. (estimate)
15questions here
3free pages
1concept
11%of the exam
Questions 11–15
- 11
A technology program is transitioning from project delivery to operations. The program's benefits realization plan defines the benefit as 'reducing customer support ticket volume by 20% within three months of the new self-service portal launch.' The portal has been live for three months, and ticket volume has decreased by 18%. The program manager is conducting the benefits transition review. Which action is most appropriate?
Select an answer first - 12
A healthcare program is transitioning from multiple component projects to steady-state operations. The benefits realization plan defines a 15% reduction in patient readmission rates as the key benefit. The final component project has closed, and the program manager is conducting the benefits transition. The readmission data for the first three months shows a 12% reduction, which is below the 15% target. The program sponsor asks the program manager to close the program. What should the program manager do?
Select an answer first - 13
During program closure, the program manager is verifying that the benefits from constituent projects have been fully realized. Which action best aligns with the benefit realization criteria verification process?
Select an answer first - 14
A manufacturing program is transitioning from project delivery to operations. The program's benefits realization plan specifies that the new production line must achieve a 95% first-pass yield rate within six months of commissioning. The line has been operational for six months, and the yield rate is 94.5%. The program manager is preparing the final benefits report. What should the program manager do?
Select an answer first - 15
A government program is transitioning from project delivery to operations. The program's benefits realization plan defines the benefit as 'increasing citizen satisfaction with online services by 20% within one year of the new portal launch.' The portal has been live for one year. The program manager receives the following data: citizen satisfaction has increased by 18% overall, but the increase is not uniform across all services. The tax filing service saw a 30% increase, while the permit application service saw only a 5% increase. The program sponsor wants to close the program, citing the overall 18% increase as close to the target. What should the program manager do?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.