Part of the Benefits Management domain, which accounts for 11% of the PGMP exam. PMI does not publish an official question count, but from its 240-minute exam (~95–160 total, ~10–18 in this domain), expect 2–4 from this objective — we provide 15 practice questions to prepare you well beyond it. (estimate)
15questions here
3free pages
1concept
11%of the exam
Questions 6–10
- 6
A transportation program is transitioning from project delivery to operations. The program's benefits realization plan specifies that the new traffic management system must reduce average commute times by 15% within one year of full deployment. The system has been fully deployed for one year, and average commute times have decreased by 14%. The program manager is preparing for the final benefits review. What should the program manager do?
Select an answer first - 7
A global logistics program is transitioning from its final component project to operations. The program's benefits realization plan specifies that the new tracking system must reduce package misrouting by at least 25% within the first quarter after go-live. The component project's closure report shows the system was delivered on time and within budget, and the project manager declares the project complete. The program manager is preparing to close the program. What should the program manager do FIRST?
Select an answer first - 8
A healthcare program is transitioning from project delivery to operations. The program's benefits realization plan defines the benefit as 'reducing patient wait times by 30% within six months of the new scheduling system launch.' The system has been live for six months. The program manager receives the following data: wait times have decreased by 28% overall, but the reduction is not uniform. The emergency department saw a 40% reduction, while the outpatient clinic saw only a 15% reduction. The program sponsor wants to close the program, citing the overall 28% reduction as close to the target. What should the program manager do?
Select an answer first - 9
A utility program is transitioning from project delivery to operations. The program's benefits realization plan specifies that the new smart meter system must reduce energy consumption by 10% within one year of full deployment. The system has been fully deployed for one year, and energy consumption has decreased by 9.5%. The program manager is preparing for the final benefits review. What should the program manager do?
Select an answer first - 10
A telecommunications program is transitioning from project delivery to operations. The program's benefits realization plan specifies that the new network must achieve a 99.99% uptime within three months of launch. The network has been live for three months, and uptime is 99.98%. The program manager is conducting the benefits transition review. What should the program manager do?
Select an answer first