PRINCE2 Practitioner (Version 7)
4.6 Managing a Stage Boundary PRINCE2-PRACTITIONER-VERSION-7 Practice Questions (Page 2)
Part of the Understand how to apply (and tailor) relevant aspects of PRINCE2 processes in context domain, which accounts for 30% of the PRINCE2-PRACTITIONER-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 150-minute exam (~60–100 total, ~18–30 in this domain), expect 3–4 from this objective — we provide 29 practice questions to prepare you well beyond it. (estimate)
Questions 6–10
- 6
A project manager is evaluating the effectiveness of the managing a stage boundary process. The project board has been approving stage plans without reviewing the details, and the project has experienced significant issues in the next stages. What is the most likely cause of this ineffectiveness?
Select an answer first - 7
A project is in stage 4 of 6. At the stage boundary, the project manager discovers that the next stage plan cannot be completed because a key resource will be unavailable. The business case is still viable. What should the project manager do?
Select an answer first - 8
Which activity is performed in the managing a stage boundary process?
Select an answer first - 9
Who is responsible for preparing the next stage plan in the managing a stage boundary process?
Select an answer first - 10
During a managing a stage boundary process, the project manager needs to update the business case with the latest forecast. According to the RACI for this process, who is responsible for performing this update?
Select an answer first
Review the revealed explanations, or continue through the curriculum.