PRINCE2 Practitioner (Version 7)
Domain 2Objective 3
2.3 Apply the Approach to the Following: Communications (3.4), People Central to the Method (3.5) PRINCE2-PRACTITIONER-VERSION-7 Practice Questions (Page 6)
Part of the Understand how to apply effective people management in successful projects domain, which accounts for 9% of the PRINCE2-PRACTITIONER-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 150-minute exam (~60–100 total, ~5–9 in this domain), expect 1–2 from this objective — we provide 32 practice questions to prepare you well beyond it. (estimate)
32questions here
7free pages
8concepts
9%of the exam
Questions 26–30
- 26
Which communication channel is most appropriate for a formal, documented decision that needs to be recorded for audit purposes?
Select an answer first - 27
A project manager is developing the communications management approach for a project that involves a high level of uncertainty. The project board wants to be kept informed of progress, but the team is concerned that too much reporting will slow them down. What is the best way to balance the project board's need for information with the team's need to focus on delivery?
Select an answer first - 28
A project manager is planning communications for a project that has a diverse range of stakeholders, including some who are external and have contractual obligations. The project manager needs to ensure that all stakeholders receive the right information at the right time. What is the most important factor to consider when developing the communications management approach?
Select an answer first - 29
A project manager is assigned to a project where the team is new to the organization and lacks experience with the technology being used. The project manager needs to lead the team effectively. Which leadership style is most appropriate in this situation?
Select an answer first - 30
A project manager is leading a project to build a new hospital wing. The project team is highly experienced and has worked together on similar projects. The project manager has a directive leadership style, but the team has expressed a preference for more autonomy. What should the project manager do to align with the principle that people are central to the method?
Select an answer first