2.2 Assess Whether an Approach to Leadership and Management of Change Within a Project, and People Affected by a Project, Is Appropriate (3.2, 3.1) PRINCE2-PRACTITIONER-VERSION-7 Practice Questions (Page 1)

Part of the Understand how to apply effective people management in successful projects domain, which accounts for 9% of the PRINCE2-PRACTITIONER-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 150-minute exam (~60–100 total, ~5–9 in this domain), expect 1–2 from this objective — we provide 18 practice questions to prepare you well beyond it. (estimate)

18questions here
4free pages
5concepts
9%of the exam

Questions 1–5

  1. 1application · medium

    A project manager is leading a project that is behind schedule. The team is demotivated and unclear about the project's vision. The project manager needs to both get the project back on track and inspire the team. Which combination of actions best demonstrates the complementary roles of leadership and management?

    Select an answer first
  2. 2expert · hard

    A project to implement a new performance management system is facing resistance from employees who fear the system will be used to punish underperformers. The project sponsor wants to proceed quickly, but the project manager is concerned about the negative impact on morale. Which approach best balances the need for speed with the need to address employee concerns?

    Select an answer first
  3. 3application · medium

    A project is introducing a new health and safety procedure that will affect all factory workers. The workers have a strong union and are suspicious of management intentions. The project manager wants to ensure smooth adoption. Which change management approach is most appropriate?

    Select an answer first
  4. 4expert · hard

    A project is introducing a new customer service process. The project has a very tight deadline and the change is relatively simple. The customer service team is experienced and generally open to change. The project manager must choose a change management approach. Which approach is most appropriate given the constraints?

    Select an answer first
  5. 5expert · hard

    A project manager is leading a project that is well-planned but the team is disengaged and the project lacks a clear sense of purpose. The project manager has strong management skills but is struggling to inspire the team. The project sponsor suggests that the project manager focus more on leadership. Which action best demonstrates a shift toward leadership?

    Select an answer first