2.2 Assess Whether an Approach to Leadership and Management of Change Within a Project, and People Affected by a Project, Is Appropriate (3.2, 3.1) PRINCE2-PRACTITIONER-VERSION-7 Practice Questions (Page 2)

Part of the Understand how to apply effective people management in successful projects domain, which accounts for 9% of the PRINCE2-PRACTITIONER-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 150-minute exam (~60–100 total, ~5–9 in this domain), expect 1–2 from this objective — we provide 18 practice questions to prepare you well beyond it. (estimate)

18questions here
4free pages
5concepts
9%of the exam

Questions 6–10

  1. 6application · medium

    A project manager is leading a project in a highly regulated environment where compliance is critical. The team is experienced and has worked together successfully before. The project manager needs to ensure adherence to strict standards while maintaining team morale. Which leadership style is most appropriate?

    Select an answer first
  2. 7application · medium

    A project to introduce a new customer relationship management (CRM) system is being planned. The sales team has expressed anxiety about the new system, fearing it will increase their workload and reduce their flexibility. The project manager wants to minimize resistance. Which approach is most likely to address the team's concerns effectively?

    Select an answer first
  3. 8expert · hard

    A project manager is leading a project that involves a major change in business processes. The project has strong support from senior management, but middle managers are resistant because they fear losing control. The project manager must decide how to manage this resistance. Which approach is most likely to be effective?

    Select an answer first
  4. 9expert · hard

    A project manager is leading a project in a matrix organization where team members report to both the project manager and their functional managers. The functional managers have different priorities and sometimes pull team members away from project work. The project manager needs to ensure the project stays on track while maintaining good relationships with functional managers. Which approach is most appropriate?

    Select an answer first
  5. 10application · medium

    A project manager is leading a cross-functional team that includes members from different departments with conflicting priorities. The project is in its early stages and the team is still forming. The project manager needs to establish clear direction and build cohesion. Which leadership style is most appropriate at this stage?

    Select an answer first