2.3 Apply the Approach to the Following: Communications (3.4), People Central to the Method (3.5) PRINCE2-PRACTITIONER-VERSION-7 Practice Questions (Page 4)

Part of the Understand how to apply effective people management in successful projects domain, which accounts for 9% of the PRINCE2-PRACTITIONER-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 150-minute exam (~60–100 total, ~5–9 in this domain), expect 1–2 from this objective — we provide 32 practice questions to prepare you well beyond it. (estimate)

32questions here
7free pages
8concepts
9%of the exam

Questions 16–20

  1. 16expert · hard

    A project manager is leading a cross-functional project with team members from different departments who have conflicting priorities. The project manager has a participative leadership style, but the team is struggling to make decisions because of the conflicting priorities. The project sponsor has asked the project manager to ensure the project stays on schedule. What should the project manager do to balance the team's need for involvement with the need for timely decisions?

    Select an answer first
  2. 17application · medium

    A project manager is leading a software upgrade for a large retail chain. The project has a diverse stakeholder group: store managers (who are busy and rarely check email), a small group of technical staff (who prefer detailed technical updates), and the finance director (who wants a high-level summary monthly). The project manager needs to ensure each group receives the right information in the right format. What should the project manager do?

    Select an answer first
  3. 18foundation · easy

    Which of the following is a key aspect of the 'people central to the method' principle?

    Select an answer first
  4. 19application · medium

    A project manager needs to communicate a complex technical change to a group of non-technical stakeholders, including the project board. The stakeholders are located in different time zones. What is the most effective communication method?

    Select an answer first
  5. 20foundation · easy

    What is the main difference between leadership and management in a project context?

    Select an answer first
Finished these 5 questions?