Part of the The PRINCE2 Agile principles, practices, and artifacts and their role in an agile context domain, which accounts for 40.0% of the PRINCE2-AGILE-PRACTITIONER-V2 exam. PeopleCert does not publish an official question count, but from its 150-minute exam (~60–100 total, ~24–24 in this domain), expect 8–8 from this objective — we provide 47 practice questions to prepare you well beyond it. (estimate)
Questions 11–15
- 11
Which planning technique in agile PRINCE2 involves grouping work into increments that can be delivered and reviewed?
Select an answer first - 12
A project manager is using PRINCE2 Agile and wants to ensure that risks are considered when planning each sprint. The team is using a risk register. Which technique is most effective for integrating risk management into sprint planning?
Select an answer first - 13
What is the role of continuous improvement in issue management within agile PRINCE2?
Select an answer first - 14
A PRINCE2 Agile project is using a burn-down chart to track progress. The project manager wants to ensure that the project board receives regular updates on progress and any issues. Which combination of techniques best supports this?
Select an answer first - 15
What is the focus of the business case practice in an agile PRINCE2 environment?
Select an answer first