Part of the The PRINCE2 Agile principles, practices, and artifacts and their role in an agile context domain, which accounts for 40.0% of the PRINCE2-AGILE-FOUNDATION-V2 exam. PeopleCert does not publish an official question count, but from its 60-minute exam (~25–40 total, ~10–10 in this domain), expect 3–3 from this objective — we provide 37 practice questions to prepare you well beyond it. (estimate)

37questions here
8free pages
11concepts
40.0%of the exam

Questions 1–5

  1. 1foundation · easy

    Which activity is a key responsibility of the Product Owner (PO) in an agile PRINCE2 project?

    Select an answer first
  2. 2expert · hard

    A large e-commerce company is running a PRINCE2 Agile project to develop a new recommendation engine. The Chief Product Owner (CPO) has been balancing the interests of different business units. The marketing department wants features that increase cross-selling, while the customer service department wants features that improve user satisfaction. The CPO has prioritized the backlog in favor of marketing features, arguing that they will generate more revenue. However, the customer service department is now reporting a high volume of complaints about the new features, and the project executive is concerned about the impact on the company's reputation. What should the CPO do?

    Select an answer first
  3. 3foundation · easy

    What is the primary role of the agile coach in a PRINCE2 Agile project?

    Select an answer first
  4. 4foundation · easy

    Which activity is a key responsibility of the Chief Product Owner (CPO) in an agile PRINCE2 project?

    Select an answer first
  5. 5expert · hard

    A government agency is running a PRINCE2 Agile project to replace its legacy tax processing system. The project executive is a senior civil servant. The Chief Product Owner (CPO) has been managing the product backlog and has been in regular contact with citizens and tax advisors. The project manager has been coordinating the delivery team, which is using Scrum. The project is in its fourth iteration, and the team has delivered several working increments. However, the project executive has just received a report from project assurance indicating that the team has been focusing on features that are not aligned with the latest government policy changes. The CPO argues that the backlog reflects the needs of the users, but the policy changes are mandatory. What should the project executive do?

    Select an answer first