Part of the The PRINCE2 Agile principles, practices, and artifacts and their role in an agile context domain, which accounts for 40.0% of the PRINCE2-AGILE-FOUNDATION-V2 exam. PeopleCert does not publish an official question count, but from its 60-minute exam (~25–40 total, ~10–10 in this domain), expect 3–3 from this objective — we provide 44 practice questions to prepare you well beyond it. (estimate)

44questions here
9free pages
15concepts
40.0%of the exam

Questions 1–5

  1. 1application · medium

    A software development project is using PRINCE2 Agile. Midway through a stage, a major competitor releases a similar product, significantly reducing the expected market value of the project's deliverables. The team is on track and within tolerances. According to the 'Continued business justification' principle, what should the project manager do?

    Select an answer first
  2. 2foundation · easy

    In PRINCE2 Agile, what is the role of the business case in supporting agile value delivery?

    Select an answer first
  3. 3application · medium

    During a sprint, a team member discovers a critical bug in a feature that was completed in a previous sprint. The bug is preventing users from completing a core task. The team is unsure whether to fix the bug immediately or continue with the current sprint's planned work. What should the team do first?

    Select an answer first
  4. 4expert · hard

    A PRINCE2 Agile project is using a rolling-wave planning approach. The project manager has a detailed plan for the current stage and a high-level plan for the next stage. The project board wants more certainty about the project's end date. How should the project manager respond?

    Select an answer first
  5. 5application · medium

    A PRINCE2 Agile project is using a burn-down chart to track progress. At the end of the second week of a 4-week stage, the chart shows that the team has completed less work than planned. The project manager needs to report progress to the project board. What is the most appropriate action?

    Select an answer first