Part of the Key concepts relating to the agile mindset, project management, and organizational change management domain, which accounts for 30.0% of the PRINCE2-AGILE-FOUNDATION-V2 exam. PeopleCert does not publish an official question count, but from its 60-minute exam (~25–40 total, ~8–8 in this domain), expect 2–2 from this objective — we provide 36 practice questions to prepare you well beyond it. (estimate)

36questions here
8free pages
9concepts
30.0%of the exam

Questions 21–25

  1. 21application · medium

    A project manager is leading a project to upgrade the company's network infrastructure. The project will require a brief downtime for all employees. The project manager has communicated the downtime schedule to the IT department and the executive team. However, the general staff are not aware of the planned downtime and are surprised when they cannot work. What is the most likely impact of this communication failure?

    Select an answer first
  2. 22expert · hard

    A bank is rolling out a new agile way of working. The change team has run extensive training and communication campaigns. However, six months later, a survey shows that while teams are holding daily stand-ups and sprints, they are still delivering large batches of work at the end of the sprint, and the 'definition of done' is rarely met. What is the most likely reason for this superficial adoption?

    Select an answer first
  3. 23application · medium

    A project manager is leading a cross-functional team on a complex IT infrastructure project. The project manager spends most of their time on detailed task tracking and status reporting to the program board. The team is experienced and capable, but they feel they are not trusted to make decisions. What is the most appropriate adjustment for the project manager to make?

    Select an answer first
  4. 24expert · hard

    A global company is implementing a new expense reporting tool. The project has strong support from the CFO and the finance team. However, the sales team, which is the primary user group, is highly resistant. They argue the new tool is too slow and will reduce their time with customers. The change manager has limited budget and time. What is the most effective strategy to increase adoption among the sales team?

    Select an answer first
  5. 25application · medium

    A retail bank is rolling out a new customer relationship management system. The project team has completed the technical build and is preparing to deploy. However, the bank's branch staff have a long-standing culture of using paper-based records and are resistant to changing their daily routines. The project manager is concerned that the technical go-live will not translate into actual adoption. Which action best addresses the situation?

    Select an answer first