Questions 11–15

  1. 11expert · hard

    A project manager is managing a project to implement a new customer service system. The project has several stakeholders, including the customer service manager, the IT department, and external vendors. The project manager wants to monitor stakeholder satisfaction, but has limited time and resources. Which approach would be most effective?

    Select an answer first
  2. 12application · medium

    A project manager is assigned to a project to upgrade the company's data storage system. The project has both internal stakeholders (IT staff, finance) and external stakeholders (a cloud service provider, regulatory auditors). The project manager is creating the stakeholder register. What is the most important factor to consider when identifying expectations?

    Select an answer first
  3. 13application · medium

    A project manager is managing a project to implement a new time-tracking system. Two weeks before the go-live date, the project manager learns that the HR department expects the system to generate custom reports that were not included in the original requirements. The project manager analyzes the situation and determines that the reports can be added with minimal effort and cost. What should the project manager do?

    Select an answer first
  4. 14foundation · easy

    A project manager is reviewing stakeholder profiles to understand what each stakeholder expects from the project. Which activity best identifies implicit expectations?

    Select an answer first
  5. 15expert · hard

    A project manager is managing a project to upgrade the company's ERP system. The project has been running for eight months, and the project manager has been providing monthly status reports to the steering committee. However, the project manager has not actively sought feedback from the end users. During the user acceptance testing (UAT) phase, the end users report that the system is difficult to use and does not meet their needs. The project manager is now facing a potential delay and budget overrun. What should the project manager have done differently?

    Select an answer first