PMIScheduling Professional (PMI-SP)
Domain 1Objective 1
Task 1 Establish Project Schedule Configuration Management Policies and Procedures Incorporating Best Practices, Regulations, Governing Standards and Organization Policies, and Procedures to Ensure Accessibility, Storage, Retrieval, Maintenance, Change Control, and Baseline Schedule Control. PMI-SP Practice Questions (Page 2)
Part of the Schedule Strategy domain, which accounts for 14% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~13–22 in this domain), expect 3–4 from this objective — we provide 30 practice questions to prepare you well beyond it. (estimate)
30questions here
6free pages
9concepts
14%of the exam
Questions 6–10
- 6
A project scheduler receives a request from a stakeholder to add a new activity to the project schedule. The project is currently in execution, and the baseline schedule has been approved. The scheduler knows that any change to the schedule must follow the established change control process. What should the scheduler do first?
Select an answer first - 7
Which practice is considered a best practice in schedule configuration management?
Select an answer first - 8
What is the first step in a typical schedule change control process?
Select an answer first - 9
What is the purpose of implementing procedures for efficient retrieval of schedule data?
Select an answer first - 10
When developing schedule configuration management procedures, what should be included to ensure alignment with organizational requirements?
Select an answer first
Finished these 5 questions?
Review the revealed explanations, or continue through the curriculum.