Part of the Schedule Planning and Development domain, which accounts for 31% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~28–48 in this domain), expect 9–16 from this objective — we provide 32 practice questions to prepare you well beyond it. (estimate)

32questions here
7free pages
11concepts
31%of the exam

Questions 31–32

  1. 31expert · hard

    A project manager is using PERT to analyze a critical activity with an expected duration of 12 days and a standard deviation of 2 days. The project manager needs to determine the probability that the activity will be completed within 16 days. Assuming a normal distribution, what is the approximate probability?

    Select an answer first
  2. 32foundation · easy

    What is a typical output of a Monte Carlo simulation for a project schedule?

    Select an answer first
Finished these 2 questions?

Review the revealed explanations, or continue through the curriculum.

No more pagesBack to PMI-SP

Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PMI-SP” is a trademark of its owner, used for identification only.