Examers.io
ExamsOrganizationsHow it worksPricingHelp & FAQ
PMI logo

PMIScheduling Professional (PMI-SP)

Domain 2Objective 2

Analyze Schedule PMI-SP Practice Questions (Page 5)

Part of the Schedule Planning and Development domain, which accounts for 31% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~28–48 in this domain), expect 9–16 from this objective — we provide 32 practice questions to prepare you well beyond it. (estimate)

32questions here
7free pages
11concepts
31%of the exam

Questions 21–25

  1. 21foundation · easy

    What is the purpose of a project buffer in the critical chain method?

    Select an answer first
  2. 22foundation · easy

    What is the primary purpose of a Resource Breakdown Structure (RBS)?

    Select an answer first
  3. 23foundation · easy

    What is the primary purpose of a Monte Carlo simulation in schedule analysis?

    Select an answer first
  4. 24foundation · easy

    What is the purpose of analyzing major milestones against the statement of work (SOW) and contract?

    Select an answer first
  5. 25application · medium

    A project manager is reviewing the schedule for a government project. The statement of work (SOW) requires that a prototype be delivered by the end of Q3. The schedule shows the prototype completion on October 5, which is 5 days into Q4. The contract does not have a penalty clause for late delivery. What should the project manager do?

    Select an answer first
Finished these 5 questions?

Review the revealed explanations, or continue through the curriculum.

Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PMI-SP” is a trademark of its owner, used for identification only.