Analyze Schedule PMI-SP Practice Questions (Page 2)

Part of the Schedule Planning and Development domain, which accounts for 31% of the PMI-SP exam. PMI does not publish an official question count, but from its 230-minute exam (~90–155 total, ~28–48 in this domain), expect 9–16 from this objective — we provide 32 practice questions to prepare you well beyond it. (estimate)

32questions here
7free pages
11concepts
31%of the exam

Questions 6–10

  1. 6foundation · easy

    When assigning resources to activities, which two factors are most important to consider?

    Select an answer first
  2. 7application · medium

    A project manager is performing a Monte Carlo simulation on a project schedule to determine the probability of completing a major milestone by the target date. The simulation runs 10,000 iterations and produces a distribution of possible completion dates. The results show that the milestone has a 75% probability of being completed by the target date. The project sponsor has set a risk tolerance of 80% for this milestone. What should the project manager do?

    Select an answer first
  3. 8expert · hard

    A project manager is analyzing a schedule with two parallel paths. Path A has a duration of 30 days and Path B has a duration of 28 days. A resource constraint on Path B will extend it to 35 days. The project manager needs to identify the critical path after considering the resource constraint. What is the critical path?

    Select an answer first
  4. 9application · medium

    A project manager is performing a quantitative schedule risk analysis for a large infrastructure project. The project has several high-risk activities with uncertain durations. The project manager wants to determine the probability of completing the project by the contractual deadline. Which technique should the project manager use?

    Select an answer first
  5. 10foundation · easy

    What is the purpose of assessing resource availability during schedule development?

    Select an answer first