Part of the Program Life Cycle Management domain, which accounts for 44% of the PGMP exam. PMI does not publish an official question count, but from its 240-minute exam (~95–160 total, ~42–70 in this domain), expect 8–14 from this objective — we provide 32 practice questions to prepare you well beyond it. (estimate)
32questions here
7free pages
10concepts
44%of the exam
Questions 31–32
- 31
A proposed change to the program's technology architecture would improve long-term scalability but would delay the delivery of a component that is critical to an early benefit. The change has been requested by the technology lead, and the program's governance framework requires a formal impact assessment. What should the program manager do?
Select an answer first - 32
A program manager is consolidating data from multiple components for a monthly performance report. The components use different reporting tools and formats. The program's reporting plan specifies a standard template, but one component lead has been submitting data in a different format, causing delays in consolidation. The program manager needs to ensure timely and accurate reporting. What should the program manager do?
Select an answer first
Finished these 2 questions?
Review the revealed explanations, or continue through the curriculum.
No more pagesBack to PGMP
Free Basic Practice is a study aid with revealable answers — not a scored exam. Examers.io is independent and not affiliated with or endorsed by PMI. “PGMP” is a trademark of its owner, used for identification only.