Part of the Program Life Cycle Management domain, which accounts for 44% of the PGMP exam. PMI does not publish an official question count, but from its 240-minute exam (~95–160 total, ~42–70 in this domain), expect 8–14 from this objective — we provide 32 practice questions to prepare you well beyond it. (estimate)
32questions here
7free pages
10concepts
44%of the exam
Questions 21–25
- 21
A program manager needs to consolidate data from multiple component projects into a single dashboard for the steering committee. The components use different reporting formats and tools. The program's reporting plan specifies a standard template for progress reports. What should the program manager do to ensure consistent and effective monitoring?
Select an answer first - 22
A variance analysis reveals that a component is behind schedule due to a shortage of skilled testers. The program has a pool of testers who are currently assigned to a component that is ahead of schedule. The program manager needs to update the program plan to address the schedule variance. What should the program manager do?
Select an answer first - 23
What is the primary goal of managing risks in a program?
Select an answer first - 24
Which of the following is an example of a program-level issue that would be managed through program issue management?
Select an answer first - 25
Which document outlines how risks will be identified, analyzed, and responded to in a program?
Select an answer first