Part of the Program Life Cycle Management domain, which accounts for 44% of the PGMP exam. PMI does not publish an official question count, but from its 240-minute exam (~95–160 total, ~42–70 in this domain), expect 8–14 from this objective — we provide 32 practice questions to prepare you well beyond it. (estimate)
32questions here
7free pages
10concepts
44%of the exam
Questions 26–30
- 26
Which activity is part of evaluating program status?
Select an answer first - 27
What is the purpose of approving the closure of a constituent project in a program?
Select an answer first - 28
What is the purpose of the change management plan in a program?
Select an answer first - 29
What is the primary purpose of evaluating program status during the Monitoring & Controlling phase?
Select an answer first - 30
A program manager is preparing the quarterly performance report for the steering committee. The report must include actual versus planned values for scope, quality, cost, schedule, and resource data. The program's cost performance index (CPI) is 0.95, and the schedule performance index (SPI) is 0.90. The program's quality metrics are within acceptable thresholds. The program manager notices that the resource utilization is above planned levels, which is driving the cost overrun. What should the program manager include in the report?
Select an answer first