PRINCE2 Practitioner (Version 7)
4.1 Directing a Project PRINCE2-PRACTITIONER-VERSION-7 Practice Questions (Page 3)
Part of the Understand how to apply (and tailor) relevant aspects of PRINCE2 processes in context domain, which accounts for 30% of the PRINCE2-PRACTITIONER-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 150-minute exam (~60–100 total, ~18–30 in this domain), expect 3–4 from this objective — we provide 23 practice questions to prepare you well beyond it. (estimate)
Questions 11–15
- 11
What is the primary purpose of the directing a project process in PRINCE2?
Select an answer first - 12
During a delivery stage, the project manager forecasts that the stage will exceed its cost tolerance. The project manager prepares an exception plan and submits it to the project board. What is the project board's responsibility in this situation?
Select an answer first - 13
Which management product is an input to the 'Authorize initiation' activity in the directing a project process?
Select an answer first - 14
What is the key criterion for determining whether the directing a project process is fit for purpose in a given project?
Select an answer first - 15
How can the directing a project process be tailored for a small, low-risk project?
Select an answer first
Review the revealed explanations, or continue through the curriculum.