Part of the Understand how to apply (and tailor) relevant aspects of PRINCE2 processes in context domain, which accounts for 30% of the PRINCE2-PRACTITIONER-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 150-minute exam (~60–100 total, ~18–30 in this domain), expect 3–4 from this objective — we provide 31 practice questions to prepare you well beyond it. (estimate)

31questions here
7free pages
7concepts
30%of the exam

Questions 26–30

  1. 26application · medium

    In a project, the project manager is the only person assigned to the role of project support. During a stage, the project manager is also responsible for preparing checkpoint reports and maintaining the issue register. According to PRINCE2, which role is accountable for the 'manage by stages' activity in controlling a stage?

    Select an answer first
  2. 27application · medium

    A project manager is controlling a stage where the team is co-located and communicates daily. The project manager is considering whether to hold formal checkpoint meetings or rely on daily stand-ups. According to PRINCE2, what is the key consideration when deciding on the format of checkpoint reports?

    Select an answer first
  3. 28foundation · easy

    Which activity in 'Controlling a Stage' is most likely to be tailored for a project with a very short stage duration?

    Select an answer first
  4. 29application · medium

    In a project, the project board has delegated the authority to approve work package changes to the project manager. The project manager is now responsible for approving changes that are within stage tolerances. According to PRINCE2, is this an effective tailoring of roles in controlling a stage?

    Select an answer first
  5. 30foundation · easy

    In the 'Controlling a Stage' process, who is responsible for authorizing work packages?

    Select an answer first