4.4 Controlling a Stage PRINCE2-PRACTITIONER-VERSION-7 Practice Questions (Page 5)

Part of the Understand how to apply (and tailor) relevant aspects of PRINCE2 processes in context domain, which accounts for 30% of the PRINCE2-PRACTITIONER-VERSION-7 exam. PeopleCert does not publish an official question count, but from its 150-minute exam (~60–100 total, ~18–30 in this domain), expect 3–4 from this objective — we provide 31 practice questions to prepare you well beyond it. (estimate)

31questions here
7free pages
7concepts
30%of the exam

Questions 21–25

  1. 21application · medium

    A project manager is controlling a stage where the project board has set very tight tolerances for time and cost. The project manager is concerned that the tolerances are too tight to allow effective management. What is the most appropriate action for the project manager?

    Select an answer first
  2. 22expert · hard

    A project manager is controlling a stage where a new risk has been identified that could have a significant impact on the stage's objectives. The project manager needs to decide whether to take action now or wait for more information. According to PRINCE2, which practice is most directly applied when the project manager evaluates the risk and decides on a response?

    Select an answer first
  3. 23application · medium

    During a stage, a team manager reports that a work package is likely to be delayed by two weeks due to a supplier issue. The project manager reviews the stage plan and determines that the delay will not affect the stage's end date. According to PRINCE2, what is the project manager's first action in controlling a stage?

    Select an answer first
  4. 24foundation · easy

    In a project where the project manager is also the team manager, which role from the 'Controlling a Stage' RACI table is most likely to be combined?

    Select an answer first
  5. 25foundation · easy

    What is the primary purpose of the 'Controlling a Stage' process in PRINCE2?

    Select an answer first