PRINCE2 Project Management PRINCE2-AGILE-PRACTITIONER-V2 Practice Questions (Page 3)

Part of the Key concepts relating to the agile mindset, project management, and organizational change management domain, which accounts for 30.0% of the PRINCE2-AGILE-PRACTITIONER-V2 exam. PeopleCert does not publish an official question count, but from its 150-minute exam (~60–100 total, ~18–18 in this domain), expect 5–5 from this objective — we provide 23 practice questions to prepare you well beyond it. (estimate)

23questions here
5free pages
5concepts
30.0%of the exam

Questions 11–15

  1. 11application · easy

    A construction company is building a new office block. The work is expected to take 18 months, and the building will be a unique asset for the company. After the building is completed, the project team will be disbanded. Which characteristic of a project is most clearly demonstrated by the team being disbanded after completion?

    Select an answer first
  2. 12foundation · easy

    Which statement best defines a 'project' as used in PRINCE2?

    Select an answer first
  3. 13expert · hard

    A project manager is leading a project to upgrade a legacy system. The project is running behind schedule, and the sponsor has said that the launch date is fixed and cannot be moved. The project manager has identified that the only way to meet the date is to reduce the amount of user acceptance testing (UAT), which could increase the risk of defects being found after launch. The sponsor has also stated that the system must be reliable. Which performance target should the project manager prioritize, and what is the most appropriate action?

    Select an answer first
  4. 14expert · hard

    A project to build a new bridge is underway. The project has a fixed budget and a fixed completion date. During construction, unexpected geological conditions are discovered, which will require additional work and increase costs. The project manager has identified that the project will exceed its budget unless the scope is reduced. However, reducing the scope will mean the bridge will not have the planned number of lanes, which will reduce the traffic capacity and the expected economic benefits. Which performance targets are in conflict, and what is the most appropriate action for the project manager?

    Select an answer first
  5. 15application · medium

    A large retail bank is undertaking a major digital transformation. The transformation is being managed as a collection of projects and programs, including a new mobile banking app, a core system upgrade, and a data analytics program. The bank's executive committee reviews the entire collection to ensure it aligns with the bank's strategic goals and to prioritize investments. In which context is the mobile banking app project being managed?

    Select an answer first