Part of the Key concepts relating to the agile mindset, project management, and organizational change management domain, which accounts for 30.0% of the PRINCE2-AGILE-PRACTITIONER-V2 exam. PeopleCert does not publish an official question count, but from its 150-minute exam (~60–100 total, ~18–18 in this domain), expect 5–5 from this objective — we provide 23 practice questions to prepare you well beyond it. (estimate)

23questions here
5free pages
5concepts
30.0%of the exam

Questions 1–5

  1. 1foundation · easy

    How do the five integrated elements of PRINCE2 work together?

    Select an answer first
  2. 2application · medium

    A project manager is setting up a new PRINCE2 project. She has identified the project's stakeholders, defined the project's approach to tailoring, and is now planning how to manage the day-to-day work. Which of the five integrated elements of PRINCE2 is she primarily addressing when she plans how to manage the day-to-day work?

    Select an answer first
  3. 3foundation · easy

    In which context can PRINCE2 be applied?

    Select an answer first
  4. 4application · medium

    A project manager is reviewing the status of a construction project. The project is on schedule, but the cost of materials has increased, pushing the project over budget. The project manager must decide whether to reduce the scope of the work or request additional funding. Which two performance targets are in direct conflict in this scenario?

    Select an answer first
  5. 5application · medium

    A company is launching a new customer loyalty app. The project manager has been told to keep the launch date fixed for the holiday season, but the marketing team keeps requesting new features. The budget is tight, and the CEO has emphasized that the app must not harm the brand's reputation for reliability. Which performance target should the project manager treat as the highest priority when making trade-off decisions?

    Select an answer first